THE CLIENT
Born in 1999, the Client is a private energy operator in Italy on both electricity and natural gas with about 400.000 clients and power plants for more than 3.200 MW of installed power.
THE CLIENT'S REQUEST
The Client aims to reduce the disposal cost related to the waste water produced in the new Combined Cycle Gas Turbine power plant based in South Italy.
THE SOLUTION
Evaporation technology: 3 x AC F 40 FF + 3 x AC R 6 FF
Construction material: UNS S32750
Overall dimensions on the ground: 3 x 15 sqm + 3 x 9.9 sqm
ANALYSIS OF MAIN PARAMETERS

PROCESS DIAGRAM

RESULTS
- Water recovery: ∿97%
- Concentration factor: 40 times
- Distillate recycled as plant service water and for demineralized water production on steam cycle
- Very high disposal cost reduction
- Zero Liquid Discharge
- Water recovery: ∿97%
- Concentration factor: 40 times
- Distillate recycled as plant service water and for demineralized water production on steam cycle
- Very high disposal cost reduction
- Zero Liquid Discharge
Hot/cold water and forced circulation evaporators
Hot/cold water scraped evaporators/crystallisers